Back to works

Interconnection of a CCGT Natural Gas Plant in Larissa

Share:

Interconnection of a CCGT Natural Gas Plant in Larissa

Requirements

This Project concerns the interconnection of a combined-cycle natural gas plant with a nominal capacity of 870 MW, which constitutes a base unit for the electricity network. The interconnection should therefore be designed with a high degree of reliability, with a view to minimising costs as well.

Client

ΛΑΡΙΣΑ ΘΕΡΜΟΗΛΕΚΤΡΙΚΗ ΜΑΕ - IP Innovative Power

ΛΑΡΙΣΑ ΘΕΡΜΟΗΛΕΚΤΡΙΚΗ ΜΑΕ - IP Innovative Power

ipinnovativepower.com
Pair of 400kV Overhead Transmission Lines

28 km

Pair of 400kV Overhead Transmission Lines

The Challenge

The customer was initially oriented towards alternative interconnection solutions which were difficult to implement, such as routing through a number of private properties. The main challenge we faced was the design of two electricity transmission lines covering a distance of many kilometres, in a way that would ensure their implementation with as few obstacles as possible.

The Solution

The project area was studied thoroughly and all plant interconnection scenarios were examined, taking into account the topology of the electricity transmission network. We came up with a technically optimal solution that reduces the properties involved by at least 15 times, also causing the minimum possible disturbance to local residents.

Related Services

  • Preliminary suitability study
  • Study for the Environmental Impact Assessment
  • Final Design to be approved by IPTO

Based on the design followed, the operation was made significantly simpler and the prospects for its completion were improved.

  • Starting Date

    October 2021

  • Project Completion

    Ongoing

  • Industry

    Power plant development companies

We are trusted

Terna energeiaki
Iberdrola
Copezouzos group
Innovative power
Motor oil
Edf
Intrakat
Kiefer
Enteka
Ventus ate
Protasis
Maximus terra
Hlmekat
Atermon
Alternus
Afcon

Talk to
our engineers today!