Interconnection of a Photovoltaic Plant 150kV in Kilkis, Central Macedonia


Challenges
Timely and accurate redesign of the new high-voltage transmission line.
Method of project completion
Taking into account the existing critical infrastructure in the area of interest and following multiple meetings with the client and relevant stakeholders, we completed the redesign of the new 150 kV transmission line accurately and on time, securing prompt positive approval from the authorities.
Related Services
- Preliminary Suitability Studies
Delivery of the new design for the high-voltage interconnection line, accurately and on schedule, ensuring prompt positive approval from the competent authorities and making the entire project complete and viable.
Starting Date
December 2024
Project Completion
February 2025