Interconnection of a Photovoltaic Plant 400kV in Kilkis, Central Macedonia

Requirements

The development of a reliable and robust interconnection system to ensure the uninterrupted connection of the new Photovoltaic Plant to the Hellenic Electricity Transmission System.

Client

ATERMON

ATERMON


Challenges

The design of an extensive overhead network that fully complies with environmental and spatial requirements while simultaneously ensuring the techno-economic optimization of the project. Key challenges included the presence of numerous existing and under-development photovoltaic parks in the area, the development of other overhead networks, and the proximity to existing critical infrastructure.

Method of project completion

Taking into account all environmental and spatial requirements, and focusing on the technical soundness and reliability of the new 400 kV transmission line, we completed its design accurately and on time, securing prompt positive approval from the authorities.

Related Services

  • Evaluation of Energy Project Interconnection
  • Interconnection Line Study for Inclusion in the Environmental Impact Assessment (EIA)
  • Preliminary Suitability Studies

Delivery of the pivotal design of the interconnection project, accurately and on schedule, ensuring prompt positive approval from the competent authorities.

  • Starting Date

    April 2023

  • Project Completion

    July 2024

  • Industry

    Power plant development companies

We are trusted

Terna energeiaki
Iberdrola
Copezouzos group
Innovative power
Motor oil
Edf
Intrakat
Kiefer
Enteka
Ventus ate
Protasis
Maximus terra
Hlmekat
Atermon new logo
Alternus
Afcon

Talk to
our engineers today!